Updates
We Are Open!
November 2023
We now have our heavy duty goods lift installed.
October 2023 - Part 2
Opening This Week
We are ready to open!
October 2023 - Part 1
Almost ready to open
We are adding the finishing touches to our new store and are almost ready to open.
September 2023 - Part 2
New Store Coming Soon to Halesowen
Things are moving fast. We have a new paint job underway, the units are all installed, the reception is getting there and we have a new fire escape for the top floor.
September 2023 - Part 1
New Store Coming Soon to Halesowen
We're making great progress with our new Self Storage facility in Halesowen. The mezzanine floor, including the stairs is in and the electrics are being installed.
August 2023
New Store Coming Soon to Halesowen
We've been hard at work planning the opening of our second Self Storage facility. We've renovated the building, including a new roof and have now started fitting it out. We're on course to open our Halesowen store this October.
50% Off for the First Twelve Weeks!
To celebrate our first birthday we are offering 50% off for the first twelve weeks for any units, 50 Sq Ft and below. Get a Quote Now
October 2020
We've been open for just under 2 months now and it's been great. We have rented most of our offices already but have two offices left. If you would like a viewing please get in touch.
September 2020
We're brand new, our Covid 19 safety precautions are in place and we are open for business.
Week 18
External building, car park markings and internal painting all complete. We are ready to open.
Week 17
Offices carpeted, finished and ready. Finishing touches to the building taking shape. Almost ready to open.
Week 16
Self storage units installed, bathrooms and offices almost ready.
Week 15
Outside of the building being painted in our brand colours.
Week 14
More storage units going up and new kitchen for the offices going in.
Week 13
Storage units going up, offices being painted, new fire doors installed.
Week 12
Security gate installation finished, CCTV system installation, roller shutter door installation.
Week 11
Security gate installation, Ground Floor lighting and painting.
Week 10
Fence installation completed, new fire escape stairs installed, office damp proofed and more entrances opened up.
Week 9
Rubbish clear up, fence installation and office fit out.
Week 8
Office entrances, layout, fit out and electrics started.
Week 7
Lift installation continues. Entrance and doorways opening up.
Week 6
Lift installation started. It's a big, heavy, convenient lift.
Week 5
Mezzanine floor painting now complete. Ready to install the lift and self storage units. Progress made with electrics on the ground floor.
Week 4
Painting the mezzanine floor started. Electrics for the ground floor and offices started.
Week 3
Mezzanine floor and stairs installed.
Week 2
Mezzanine floor installation.
Week 1
Mezzanine floor arrives and new roof installed.
Before We Started
Before we could even start planning or building our new self storage facility in West Bromwich we had so much work to do.